Alta Mesa Road Bridge Replacement at Laguna Creek

The proposed project consists of replacement of an existing two-lane concrete deck on timber stringers bridge, with a new two-lane concrete bridge on Alta Mesa Road at Laguna Creek north of State Route 104.

Tentative Schedule

  • Preliminary Study: 2011 to 2013.
  • Environmental Study: 2011 to 2016.
  • Design: 2014 to 2019.
  • Right-of-Way Acquisition: 2018 to 2019.
  • Construction: May 2020.

Project Links

Funding

Estimated construction costs are $5 million. Project costs will be covered with Federal Highway Bridge Project (HBP) funds and the Road Fund.