Folsom Boulevard and Cottage Way Sidewalk Infill

​This project will improve pedestrian accessibility by filling in sidewalk gaps at one location on the north side of Folsom Boulevard in Cordova (District 5) and at several locations along Cottage Way in Arden Arcade (District 3).  The project includes installation of ~800' of sidewalk separated from the roadway by landscaped frontage with decorative street lights along the north side of Folsom Boulevard between Mira Del Rio Drive and Butterfield Way, ~180' of sidewalk along the north
side of Cottage Way east of Fulton Avenue, and ~800' of sidewalk and street lights along the north side of Cottage Way from west of Trimble Way to east Terrace Drive.

Project Benefits

Improved safety for pedestrians: sidewalks and street lighting.

Project Schedule

  • Preliminary Design: 2016
  • Environmental Review: 2016 to 2017
  • OPER Control No.: PLER2016-00069
  • CEQA Determination & Notice of Exemption - March 15, 2017
  • CEQA Determination: Categorical Exclusion - October 3, 2017
  • Final Design: 2019
  • Right-of-Way Acquisition: 2018 to 2019
  • Construction: Summer 2020 to Fall 2020

Project Links

Funding

Estimated construction cost is $1.3 million, with funding provided by the Federal Congestion Management Air Quality (CMAQ) Program and a local percentage match from the Sacramento County Measure A Sales Tax.

Contact Information

Stan Sorensen, Senior Civil Engineer