Tentative Schedule

  • Preliminary Engineering:2024
  • Environmental Clearance: 2025
  • Design: 2025 to 2026
  • Right-of-Way Acquisition: 2025 to 2026
  • Construction: 2027

Funding

Estimated total project costs are $3,645,000 and will be provided by Measure A and Developer Fee Funding