Project Description
This project will widen Power Line Road and West Elverta Road from a two-lane local road to a two-lane arterial with a center turn lane. Widening will occur from Allbaugh Drive to West Elverta Rd and 2100’ east of the intersection along West Elverta Road. The roadway improvements will include curb and gutter, drainage facilities, and pavement overlay.
Project Schedule
• Design: 2022-2023
• Construction: 2023
Funding
Estimated total project costs are $5,574,000 and will be provided by Metro Air Park Impact Fee Program.
Contact Information
Jenny Singh, Senior Civil Engineer
Phone: 916-874-6092
Email: singhje@saccounty.net
Nestor Hernandez, Associate Civil Engineer
Phone: 916-875-5415
Email: hernandezne@saccounty.net