This project will install curb, gutter, sidewalk infill, curb ramps, and  street lighting on various locations along Edison Avenue (E Country Club -Watt Ave), El Camino Ave (Gunn Rd-Fair Oaks Blvd), Hurley Wy (Dealynn St-Gannon Dr), Manzanita Ave (Hilltop Dr-Auburn Blvd), and Marconi Ave (Eastern Ave -Root Ave)

Project Benefits

• Improved pedestrian safety and mobility throughout the project area by installing street lights, and constructing continuous sidewalks, and installing ADA compliant sidewalk ramps at corners.

Project Schedule

Preliminary Design: 2020 to 2021   
Environmental review: 2020 to 2021  
• PER Control No.: PLER2019-00076
• CEQA Environmental Action at Board of Supervisors Meeting: TBD
• NEPA Determination: TBD
Final Design: 2021 to 2022 
Right-of-Way Acquisition: 2021 to 2022
Construction: 2023​

Project Map


 

Funding

The estimated construction cost for the project is $2,500,000.  The project is funded through the Highway Safety Improvement Program (HSIP) 2018-2