Project Description
This project will improve bicycle and pedestrian safety and mobility through the mixed use of developments between Munroe and Howe. Fair Oak Blvd will be reduced to 4 lanes and separated bike lanes will be added. Sidewalks impeded by utilities will be widened and 2 new traffic signals will be added. Additionally, the Fair Oaks Blvd/Fulton Ave intersection will be modified.
Project Schedule
- Preliminary Engineering: 2022
- Environmental Clearance: 2021
- Design: 2023 to 2025
- Right-of-Way Acquisition: 2023 to 2025
- Construction: 2025 to 2026
Project Map
Project Links
Funding
Estimated total construction cost is 10$ million and will be funded by a Congestion Mitigation and Air Quality (CMAQ) grant, a Rural Surface Transportation Program (RSTP) grant, Measure A and Developer Fee Funding.