Project Description
This project will install traffic signals at the southbound and northbound off-ramps at the I-5/Metro Air Parkway Interchange.
Tentative Schedule
- Preliminary Engineering: 2023
- Environmental Clearance: Fall 2024
- Design: 2023 to 2024
- Right-of-Way Acquisition: N/A
- Construction: 2025
Funding
The estimated construction cost for the project is $720,000. The project is funded through the Metro Air Park Community Financial District.