Power Inn Road Project

Description

The Sacramento County Department of Transportation is moving forward with construction of the Power Inn Road project.

Timeline

  • Anticipated Board of Supervisors approval: December 2020
  • Anticipated Bid announcement: February 2021
  • Anticipated awarding of the contract: March 2021
  • Anticipated construction schedule: April 15, 2021 to December 31, 2021

Project work

  • Install curbs, gutters & sidewalks, landscaped median & planter, pedestrian crossings, ADA ramps, update drainage system.

Traffic
During construction, one through lane in each direction will be maintained at all times and two through lanes in each direction will be maintained during the morning and evening rush hours. Access will be maintained to all residences and businesses during construction. Pedestrian and bicycle access will also be maintained.

Map

 

Contact us

For more information:

Crystal Tu

Civil Engineer

E-mail: tuc@saccounty.net

Phone: 916-874-6869