Project Description
This project will widen Power Line Road from a two-lane local road to a two-lane arterial with a center turn lane. Widening will occur from Skyking Road to Serna Drive. The roadway improvements will include curb and gutter, drainage facilities, and pavement overlay.
Project Schedule
• Design: 2020
• Construction: 2021
Funding
Estimated total project costs are $3,372,000 and will be provided by Metro Air Park Development Impact Fee Program.