This project will improve street lighting along M Street between Rio Linda Blvd and 6th Street. The project includes installation of new decorative street lights.
Sign up to receive project newsletters and updates by email and text messages!
Project Benefits
· Improved safety for bicyclists and pedestrians by adding new street lighting.
Project Schedule
· Preliminary Design: 2023
· Environmental Review: 2023
-OPER Control No.: PLER 2023-00074
-NEPA Determination: Categorical Exclusion - July 2023
· Final Design: 2024
Construction: 2024
Project Map
Funding
Estimated construction cost is $541,950, with funding provided by the Sacramento Housing and Redevelopment Agency (SHRA) and Local Funds.