The Sacramento County Department of Transportation is designing and moving forward with the Arden Arcade and Carmichael area sidewalk infill project.
Timeline
Anticipated Board of Supervisors approval: December 2021
Anticipated Bid announcement: February 2022
Anticipated awarding of the contract: March 2022
Anticipated construction schedule: April 15, 2022 to December 31, 2022
Project work
- Install curbs, gutters & sidewalks, landscaped median & planter, pedestrian crossings, ADA ramps, update drainage system.
- Various Locations: Edison Ave, El Camino Ave, Hurley Way, Manzanita Ave, Marconi Ave