Background
This project will improve pedestrian and resurface roadway pavement facilities at various locations in South Sacramento (District 2). The project includes the installation of a widened sidewalk, speed humps, refreshed striping, sidewalk ramps to current ADA standards, and the installation of a median island and video detection at MLK Boulevard and 44th Avenue.
Sign up to receive project newsletters and updates by email and text messages!
Project Benefits
- Improved safety for bicyclists and pedestrians at MLK Boulevard and 44th Avenue by adding a median island and video detection for the existing midblock crossing.
- Improved safety for pedestrians and the disabled by adding ADA compliant sidewalk ramps at street crossings.
Project Schedule
- Preliminary Design: 2021
- Environmental Review: 2021
- NEPA Determination: Categorical Exclusion - January 2022
- Right-of-Way Acquisition: 2024
- Final Design: 2024
- Construction: 2024
Project Map
Project Area
Funding
Estimated construction cost is approximately $1,326,269, with funding provided by a State Active Transportation Program (ATP).
Newsletter
October 2024
Contact Information
Spencer Ord, Senior Civil Engineer
Phone: 916-876-6601
Email: ords@saccounty.gov
Josh Iniguez, Associate Civil Engineer
Phone: 916-874-5024
Email: iniguezj@saccounty.gov
Thomas Andrew, Resident Engineer
Phone: 916-214-6861
Email: andrewt@saccounty.gov