Project Description
This project will construct new sidewalk to close gaps on the west side of Watt Ave between Don Julio Blvd and Elkhorn Blvd. This project also includes street lighting.
Tentative Schedule
• Preliminary Engineering: 2021 to 2022
• Environmental Clearance: 2023
• Design: 2023
• Right-of-Way Acquisition: 2023
• Construction: 2024
Funding
The estimated construction cost for the project is $930,000. The project is funded by Measure A Sales Tax and the Sacramento County Transportation Development Fee Program (SCTDF).
Contact Information
Jenny Singh, Senior Civil Engineer
Phone: 916-874-6092
Email: singhje@saccounty.net
Gabriel Flores, Assoc Civil Engineer
(916) 875-1612
floresga@saccounty.gov