Twin Cities Road Bridge Replacement

Subscribe to receive updates

The proposed project consists of replacement of the existing moveable swing, steel bridge with a new concrete structure and concrete approaches at Twin Cities Road at Snodgrass Slough, 2.0 miles east of River Road in south Sacramento County.

Tentative Schedule

  • Environmental Study: 2022.
  • Final Design: 2022 to 2027.
  • Right-of-Way Acquisition: 2022 to 2025.
  • Construction: 2027 to 2029​.

Funding

Estimated construction costs are $16 million. Project costs will be covered with Federal Highway Bridge Project (HBP) funds, SB1 funds, and the Road Fund.

Contact Information​

Jenny Singh, Senior Civil Engineer
Phone: 916-874-6092
Email: singhje@saccounty.net